Scope Fixed First, Residents Asked Later

24th November 2026

In an Edinburgh mixed tenure scheme, scope and cost were fixed before residents were consulted, leaving minority owners with a vote that does not count and a £25,000 estimate. 

 

At a glance 

  • The Mixed Tenure Improvement Service covers about 1,200 properties in one Edinburgh neighbourhood, where the council owns around half of the homes. 

  • A building survey took 918 days to be issued, and the cost estimate for one flat is £25,000 after government grants. 

  • Success in Scotland's area based schemes is counted in measures installed, not in outcomes for residents such as comfort, damp and mould, and bills. 

Retrofit in mixed tenure blocks works when residents are involved at every stage, from before scope and cost are fixed through to snagging, with someone alongside them throughout the process. Where the majority owner designs the scheme and manages the contracts, other owners and tenants meet it as a letter, a vote and a bill. 

Edinburgh's Mixed Tenure Improvement Service (MTIS) shows the effect of decisions made first and communicated afterwards. A letter in summer 2023 announced new roofs and external wall insulation across about 1,200 properties in Lochend, a neighbourhood targeted because of high levels of deprivation, where the council owns around half of the homes. 

Melissa Esquerre, a designer, researcher and 2025 Churchill Fellow, owns one flat in a block the council otherwise owns. Her experience of the scheme, and the report that followed her fellowship, inform what follows. The figures are those reported by residents.  

A vote that does not count 

Under Scottish tenement law the majority decides. An owner of one flat in a block the council otherwise owns receives the paperwork and a vote that does not count. Owners in the majority vote on a scope that is already set, all or nothing. 

Residents are seeking a route to raise problems before works start, joint sign-off of completed works by owners, and independent checks tied to funding. Some neighbours currently carry out quality control themselves.  

Delay and cost 

The financial detail arrived slowly. A building survey took 918 days to be issued, longer than the 793 days taken to build the Eiffel Tower. The cost estimate came at the end of September: £25,000 after government grants, made up of £20,000 for works and a £5,000 management fee, 20% of the total, payable to the council. 

Works to the block are expected to start in early 2027, more than three years after the first letter. The timeline, the proposed solution and the financing conditions changed several times in between. 

Cost falls hardest where resources are lowest. Reported figures show 154 properties sold across the areas where the programme is live, over 30 of them in this neighbourhood, and the number is expected to rise. Other households face payment plans running for many years. The neighbourhood has also seen evictions of private tenants and of people in debt. 

Take-up among owners who do have a vote is low, because the offer does not make financial sense and the benefits cannot be seen. Interest on payment plans fell from 4% to 0% after residents campaigned through a tenant and community union that was active before the scheme was announced.  

Measures installed, outcomes unmeasured 

Success in Scotland's area based schemes is counted in measures installed, which shows little about what residents gain. Owners need the cost, the expected savings and whether the home will be warmer with less damp, so they can compare a retrofit against the monthly cost of servicing a debt. 

No temperature or humidity measurement was taken before works, which makes later comparison difficult. Residents in retrofitted homes are using humidity sensors to monitor conditions. Ventilation upgrades are part of the scheme, but some residents have had to press for the right ventilation to be installed. 

From a Healthy Homes Hub perspective, baseline measurement of temperature, humidity and energy bills is what allows a change in indoor conditions to be shown rather than assumed.  

Practice in Spain and elsewhere in Europe 

Visits to countries including Denmark, Spain and Sweden during a 2025 Churchill Fellowship found different practice. In the places visited, retrofit is planned for whole neighbourhoods, including streets and communal spaces. It starts with what residents need, such as lifts or the removal of entrance steps in apartment blocks built cheaply decades ago, before insulation is discussed. 

In the Basque Country, a one-stop shop sits in a prominent public place, staffed by an architect, a lawyer and caseworkers who help neighbours reach joint decisions and apply for funding, and who stay with them throughout. A healthy homes office in Getafe, near Madrid, offers advice on bills and fuel poverty, retrofit support and help in setting up energy communities. The networks behind these projects share mistakes openly.  

Retrofit as a service 

Residents experience retrofit as a service that starts with a letter and continues after snagging, while a contractor may be on site for a few months. Trust is built or lost at specific points: the first letter, an auto reply, a date that moves without explanation and a fault with no clear route to redress. 

Scotland has 1.9 million homes to upgrade, and each household decides whether to trust the organisation proposing the work. Funding for area based schemes pays for the works, with nothing set aside for building trust before they are designed. Residents' time at council meetings and committees is also unbudgeted.  

Practical steps for housing providers 

  • Involve residents before scope, cost and contractor are fixed, and state plainly what can change and what is fixed. 

  • Budget for participation, covering residents' time and meeting times that people can attend. 

  • Share survey results, a cost estimate, the expected effect on bills, warmth and damp, and impartial financing advice early, before any vote. 

  • Measure temperature, humidity and energy bills before works begin, so residents and landlords can compare conditions afterwards. 

  • Report outcomes alongside measures installed, and build independent checks of completed works into delivery and funding conditions. 

  • Provide a named contact, a physical point of access and a clear route for redress when dates move or work goes wrong. 

  • Arrange visits to completed schemes, in the UK or elsewhere, so residents and decision makers can see what the works mean in practice. 

  • People not buildings: Trust, empowerment and resident participation in urban retrofit and adaptation (Churchill Fellowship report, published 30 January 2026): https://churchillfellowship.org/ideas-experts/ideas-library/people-not-buildings-trust-empowerment-and-resident-participation-in-urban-retrofit-and-adaptation/